November 15, 2020 BOD Report Update

This project, which began in 2019 completed all of the actual paving work by last November.  HSCA crews continued work related to this project which included painting all of the lot numbers and lane lines and back filling shoulder edges in the upper portion of the subdivision.  Our crews have completed all of the painting work and have only two more streets than need to have the shoulders backfilled.  This project will be completed ahead of its schedule and quite a bit under the project budget, reducing our loan liability with the USDA.

April 15, 2020 BOD Report Update

USDA and HSCA staff conducted the Yamada Contract close out inspection. It appears all documents are in place to allow USDA to authorize us to make the final payment to Yamada and this payment will basically close the contact and pay the contingency.
HSCA crews finished painting all lot numbers, private property lines, stop bars and centerlines. We should begin limited roadway shoulder dressing/banking in the very near future and are looking at the Hawaiian Beaches trailer to see if we can modify so it can “side discharge” cinder soil.

March 19, 2020

On this day, painting of lot numbers and private property lines on the newly paved roads was completed!  Big mahalo to our crew for their hard work!

January 29, 2020 BOD Report Update

Yamada and Sons Inc. completed all paving work, including our Honu Park parking lots in November.    This allows Yamada to submit their final bill which will include their retainage.      HSCA crews have completed 60% of the lot number and private property line painting, which takes us up to Manini. HSCA crews will also need to do some shoulder dressing/banking on some of the upper streets of the subdivision as the initial roadside cutback width and depth was larger than what was actually needed and we did not discover this until the first street was paved.  This work will be charged back to the USDA loan and should be completed by June.

It is clear that we will not need to borrow the entire amount of the USDA loan for this project and the new amount could be lower by approximately $300,000.  The loan term, payment amount, and whether or not we should consider adjusting payments and/or making annual additional principal only payments will be reviewed and options presented to the Board for the March, 2020 meeting.

August 21, 2019 BOD Report Update

May 19, 2019 BOD Report Update

June 19, 2019 BOD Report Update

May 15, 2019 BOD Report Update

March 20, 2019 BOD Report Update

March 7, 2019

Road Resurfacing Project Update

HSCA has successfully negotiated a contract with Yamada and Sons Inc. for the resurfacing of the subdivision streets.  Yamada and Sons has indicated that they will be prepared to start paving roads on or around May 1, 2019.   They will begin work at the top of the subdivision between Aama Street and Ina Street.

HSCA crews are now preparing streets for paving by removing vegetation from cracks in the street, sealing the cracks and removing sod and vegetation from the street edges.   The removal of about 9 inches of sod from the street edges must be done to ensure edge to edge repaving.  It also must occur just prior to paving, with HSCA crews focusing on the section between Aama Street and Ina Street during the month of March.  Our crews will make every effort to clean up after this work and Yamada and Sons is tasked with sweeping or flushing the street just prior to placing the asphalt surface.

It is expected that all streets can be paved in a four to six-month time period, weather depending, and members will be given 3 days advance notice before their street is repaved.   Each street should be paved in one day and although emergency access will be provided, there will be times when the street is unavailable due to the paving operations.  We ask for your cooperation in coordinating your activities the day your street is paved. Please call of office at (808)965-8140 if you have any questions or concerns.

February 20, 2019 BOD Report Update

January 16, 2019 BOD Report Update

December 20, 2018 BOD Report Update

October 17, 2018 BOD Report Update

September 19, 2018 BOD Report Update

August 15, 2018 BOD Report Update

July 18, 2018 BOD Report Update

June 20, 2018 BOD Report Update

May 16, 2018 BOD Report Update

April 18, 2018 BOD Report Update

March 21, 2018 BOD Report Update

February 21, 2018 BOD Report Update

January 17th, 2018 BOD Report Update

December 20th, 2017 BOD Report Update

November 15, 2017 BOD Report Update